§100-94 METHODS OF REDUCING FLOOD LOSSES

In order to accomplish its purposes, this Article includes methods and provisions for:

[1] Restricting or prohibiting uses which are dangerous to health, safety, and property due to flood hazards, or which result in damaging increases in flood heights or velocities;

[2] Requiring that uses vulnerable to floods including facilities which serve such uses, be protected against flood damage at the time of initial construction;

[3] Controlling the alteration of natural flood plains, stream channels, and natural protective barriers, which help accommodate or channel flood waters;

[4] Controlling filling, grading, dredging, and other development which may increase flood damage; and,

[5] Preventing or regulating the construction of flood barriers which will unnaturally divert flood waters or which may increase flood hazards in other areas.

§100-95 DEFINITIONS

Unless specifically defined below, words or phases used in this Article shall be interpreted so as to give them the meaning they have in common usage and to give this ordinance its most reasonable application.



APPEAL means a request for a review of the Development Regulation Officer's interpretation of any provision of this ordinance or a request for a variance.

AREA OF SHALLOW FLOODING means a designated AO, AH, or VO zone on a community's Flood Insurance Rate Map with a one percent or greater chance of flooding to an average depth of one to three feet where a clearly defined channel does not exist, where the path of flooding is unpredictable and where velocity flow may be evident.

AREA OF SPECIAL FLOOD HAZARD means the land in the flood plain within a community subject to a one percent or greater chance of flooding in any given year.

BASE FLOOD means the flood having a one percent chance of being equaled or exceeded in any given year.

BASEMENT means any area of the building having its floor below ground level on all sides.



BREAKAWAY WALL means a wall that is part of the structural support of the building and is intended through its design and construction to collapse under specific lateral loading forces without causing damage to the elevated portion of the building or supporting foundation system.

DEVELOPMENT means any man made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials located within the area of special flood hazard.

ELEVATED BUILDING means a non-basement building (i) built with the top of the elevated floor above the ground level by means of piling, columns (posts and piers) , or shear walls parallel to the flow of the water, and (ii) adequately anchored so as not to impair the structural integrity of the building during a flood up to the magnitude of the base flood. "Elevated building" also includes a building elevated by means of fill or solid foundation perimeter walls with openings sufficient to facilitate the unimpeded movement of flood waters.

FLOOD OR FLOODING means a general and temporary condition of partial or complete inundation of normally dry land areas from:

[1] The overflow of streams or rivers; or

[2] The unusual and rapid accumulation or runoff of surface waters from any source.

FLOOD INSURANCE RATE MAP (FIRM) means the official map on which the Federal Insurance Administration has delineated both the areas of special flood hazards and the risk premium zones applicable to the community.

FLOOD INSURANCE STUDY (FIS) means the official report in which the Federal Insurance Administration has provided flood profiles, as well as the Flood Boundary/Floodway Map and the water surface elevation of the base flood.

FLOOD PLAIN MANAGEMENT REGULATIONS means zoning ordinances, subdivision regulations, building codes, health regulations, special purpose ordinances (such as a flood plain ordinance, grading ordinance and erosion control ordinance) and other applications of police power. The term describes such State or local regulations, in any combination thereof, which provide standards for the purpose of flood damage prevention and reduction.

FLOODWAY means the channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than 0.2 foot.

HISTORIC STRUCTURE means any structure that is:



[1] Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;

[2] Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district preliminarily determined by the Secretary to qualify as a registered historic district;

[3] Individually listed on a State inventory of historic places in States with historic preservation programs which have been approved by the Secretary of the Interior; or

[4] Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either:

(a) By an approved State program as determined by the Secretary of the Interior; or

(b) Directly by the Secretary of the Interior in States without approved programs.

LOWEST FLOOR means the lowest floor of the lowest enclosed area [including basement]. An unfinished or flood resistant enclosure, useable solely for the parking of vehicles, building access or storage in an area other than a basement is not considered a buildings lowest floor provided that such enclosure is not built so to render the structure in violation of other applicable non-elevation design requirements.

MANUFACTURED HOME means a structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when attached to the required utilities. The term "manufactured home" does not include a "recreation vehicle".

MANUFACTURED HOME PARK OR MANUFACTURED HOME SUBDIVISION means a parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.

NEW CONSTRUCTION means structures for which the start of construction commenced on or after the effective date of a floodplain regulation adopted by a community and includes any subsequent improvements to such structures.

NEW MANUFACTURED HOME PARK OR SUBDIVISION means a manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after the effective date of the flood plain management regulations adopted by the municipality.

RECREATIONAL VEHICLE means a vehicle which is [i] built on a single chassis; [ii] 400 square feet or less when measured at the longest horizontal projections; [iii] designed to be self-propelled or permanently towable by a light duty truck; and [iv] designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.

START OF CONSTRUCTION includes substantial improvements and means the date the building permit was issued, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days of the permit date. The actual start means either the first placement of permanent construction of a structure on a site such as the pouring of a slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation, or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading and filling nor does it include the installation of streets and/or walkways, nor does it include excavation for a basement, footings or piers, or foundations or the erection of temporary forms, nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.

STRUCTURE means a walled and roofed building, a manufactured home, or a gas or liquid storage tank, that is principally above ground.

SUBSTANTIAL DAMAGE means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.

SUBSTANTIAL IMPROVEMENT means any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which exceeds 50 percent of the equalized assessed value of the structure before the "start of construction" of the improvement. This term includes structures which have incurred "substantial damage", regardless of the actual repair work performed. The term does not, however, include either:

[1] Any project for improvement of a structure to correct existing violations of State or local health, sanitary or safety code specifications which have been identified by the local code enforcement officer and which are the minimum necessary to assure safe living conditions; or

[2] Any aiteration of a "historic structure", provided that the alteration will not preclude the structure's continued designation as a "historic structure".

VARIANCE means a grant of relief from the requirements of this ordinance which permits construction in a manner that would otherwise be prohibited by this ordinance.



§100-96 LANDS TO WHICH THIS ORDINANCE APPLIES

This Article shall apply to all areas of special flood hazards within the jurisdiction of the Township.

§100-97 BASIS FOR ESTABLISHING THE AREAS OF SPECIAL FLOOD HAZARD

The areas of special flood hazard identified by the Federal Insurance Administration in a scientific and engineering report entitled "The Flood Insurance Study for the Township of Holland, Hunterdon County, New Jersey dated June 6, 2001,. with accompanying Flood Insurance Rate Maps, is hereby adopted by reference and declared to be a part of this Article. The Flood Insurance Study is on file at the office of the Clerk of this Township and is there available for public inspection.

§100-98 PENALTIES FOR NONCOMPLIANCE

No structure or land shall hereafter be constructed, located, extended, converted, or altered without full compliance with the terms of this Article and other applicable regulations. Violation of the provisions of this Article by failure to comply with any of its requirements (including violations of conditions and safeguards established in connection with conditions) shall constitute an ordinance violation. Any person who violates this ordinance or fails to comply with any of its requirements shall upon conviction thereof be fined not more than $1,000.00 or imprisoned for not more than 90 days, or both, for each violation, and in addition shall pay all costs and expenses involved in the case if allowed by law. Nothing herein contained shall prevent the Township from taking such other lawful action as is necessary to prevent or remedy any violation.

§100-99 ABROGATION AND GREATER RESTRICTIONS

This Article is not intended to repeal, abrogate, or impair any existing easements, covenants, or deed restrictions. However, where this article and other ordinance, easement, covenant, or deed restriction conflict or overlap, whichever imposes the more stringent restrictions shall prevail.

§100-100 INTERPRETATION

In the interpretation and application of this ordinance, all' provisions shall be:

[1] Considered as minimum requirements;

[2] Liberally construed in favor of the Township; and,

[3] Deemed neither to limit nor repeal any other powers granted under State statutes.

§100-101 WARNING AND DISCLAIMER OF LIABILITY

The degree of flood protection required by this ordinance is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur on rare occasions. Flood Heights may be increased by man-made or natural causes. This Article does not imply that land outside the area of special flood hazards or uses permitted within such areas will be free from flooding or flood damages.

This Article shall not create liability on the part of the Township, any officer or employee thereof or the Federal Insurance Administration, for any flood damages that result from reliance on this ordinance or any administrative decision lawfully made thereunder.



§100-102 ESTABLISHMENT OF DEVELOPMENT PERMIT

A.Development Permit shall be obtained before construction or development begins within any area of special flood hazard established in Section 100-97. Application for a Development Permit shall be made on forms furnished by the Development Regulations Officer and may include, but not be limited to; plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question; existing and proposed structures, fill, storage of materials, drainage facilities; and the location of the foregoing.

Specifically, the following information is required:

[1] Elevation referenced to the National Geodetic Vertical Datum of 1929 ("NGVD"), of the lowest floor (including basement) of all structures;

[2] Elevation referenced to NGVD 1929 to which any structure has been floodproofed.

[3] Certification by a registered professional engineer or architect that the floodproofing methods for any nonresidential structure meet the floodproofing criteria in Section 100-105 B.(2),

[4] Description of the extent to which any watercourse will be altered or relocated as a result of proposed development.

§ 100-102 DESIGNATION OF THE DEVELOPMENT REGULATIONS OFFICER

The Development Regulations Officer is hereby appointed to administer and implement this Article by granting or denying development permit applications in accordance with its provisions.

§100-103 DUTIES AND RESPONSIBILITIES OF THE DEVELOPMENT REGULATIONS OFFICER

Duties of the Development Regulations Officer shall include, but not be limited to:

A. PERMIT REVIEW

[1] Review all development permits to determine that the permit requirements of this ordinance have been satisfied.

[2] Review all development permits to determine that all necessary permits have been obtained from those Federal,

State or local governmental agencies from which prior approval is required.

[3] Review all development permits to determine if the proposed development is located in the floodway, assure that the encroachment provisions of Section 100-105 C.(1) are met.

B. USE OF OTHER BASE FLOOD AND FLOODWAY DATA

When base flood elevation and floodway data has not been provided in accordance with Section 100-97, BASIS FOR ESTABLISHING THE AREAS OF SPECIAL FLOOD HAZARD, the Development Regulations Officer shall obtain, review, and reasonably utilize any base flood elevation and floodway data available from a Federal, State or other source, in order to administer Sections 100-105 B.(1), SPECIFIC STANDARDS, Residential Construction, and 100-105 B.(2), SPECIFIC STANDARDS, Nonresidential Construction.

C. INFORMATION TO BE OBTAINED AND MAINTAINED

Information required herein shall be provided by the holder of a development permit in the form of a certification prepared by a land surveyor licensed in the State of New Jersey.

[1] Obtain and record the actual elevation (referenced to NGVD 1929 of the lowest floor (including basement) of all new or substantially improved structures, and whether or not the structure contains a basement.

[2] For all new or substantially improved floodproofed structures:

[i] verify and record the actual elevation

(referenced to NGVD 1929); and

[ii] maintain the floodproofing certifications required in Section 100-102[3].

[3] Maintain for public inspection all records pertaining to the provisions of this ordinance.

§100-104 VARIANCE PROCEDURE

A. APPEAL BOARD

[1] The Zoning Board of Adjustment of the Township as established under the Municipal Land Use Law shall hear and decide appeals and requests for variances from the requirements of this article in the manner prescribed for variances under the Municipal Land Use Law.

[2] The Zoning Board of Adjustment shall hear and decide appeals when it is alleged there is an error in any requirement, decision, or determination made by the Development Regulations Officer in the enforcement or administration of this Article.

[3] Those aggrieved by the decision of the Zoning Board of Adjustment or any taxpayer, may appeal such decision to the Superior Court of New Jersey as provided in the Rules of Court.

[4] In passing upon such applications, the Zoning Board of Adjustment shall consider all technical evaluations, all relevant factors, standards specified in other sections of this ordinance, and:

(i) the danger that materials may be swept onto other lands to the injury of others;

(ii) the danger to life and property due to flooding damage;

(iii) the susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;

(iv) the importance of the services provided by the proposed facility to the community;

(v) the necessity to the facility of a waterfront location, where applicable;

(vi) the availability of alternative locations forthe proposed use which are not subject to flooding or erosion damage;

(vii) the compatibility of the proposed use with existing and anticipated development;

(viii) the relationship of the proposed use to the comprehensive plan and flood plain management program of that area;

(ix) the safety of access to the property in times of flood for ordinary and emergency vehicles;

(x) the expected heights, velocity, duration, rate of rise, of the flood waters expected at the site., and,

(xi) the costs of providing governmental services during and after flood conditions, including maintenance and repair of public utilities and facilities such as sewer, gas, electrical, and water systems, and streets and bridges.

[5] Upon consideration of the factors of Section 4.41(4) and the purposes of this ordinance, the (appeal board) may attach such conditions to the granting of variances as it deems necessary to further the purposes of this ordinance.

[6] The Development Regulations Officer shall maintain the records of all appeal actions, including technical information, and report any variances to the Federal Insurance Administration upon request.

B. CONDITIONS FOR VARIANCES

[1] Generally, variances may be issued for new construction and substantial improvements to be erected on a lot of one-half acre or less in size contiguous to and surrounded by lots with existing structures constructed below the base flood level, providing items (i-xi) in SECTION 100-104A.(4) have been fully considered. As the lot size increases beyond the one-half acre, the technical justification required for issuing the variance increases.

[2] Variances may be issued for the repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum necessary to preserve the historic character and design of the structure.

[3] Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.

[4] Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.

[5] Variances shall only be issued upon:

(i) a showing of good and sufficient cause;

(ii) a determination that failure to grant the variance would result in exceptional hardship to the applicant; and,

(iii) a determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisances, cause fraud on or victimization of the public as identified in SECTION 100-104 A.[4], or conflict with existing local laws or ordinances.

(6) Any applicant to whom a variance is granted shall be given written notice by the Development Regulations Officer that the structure will be permitted to be built with a lowest floor elevation below the base flood elevation and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation.